The projects below represent generator infrastructure upgrades, system modernizations, and turnkey installations executed with disciplined planning and structured oversight. From broadcast facilities to mission-critical environments, each engagement reflects accountability, technical alignment, and execution when it matters most.
Project Overview
Led project management for the full decommissioning and replacement of 3 MW of emergency backup generation capacity at the Hyatt Regency Grand Reserve in Rio Grande, Puerto Rico.
The original three-week schedule was extended to nearly two months due to hurricane activity and severe storms.
Continuous on-site leadership was required to maintain safety, sequencing, and execution integrity amid repeated weather disruptions.
Scope of Work
- Decommissioning of two 1.5 MW generators
- Installation of two 2 MW Caterpillar diesel generators
- Coordination of international freight shipping and island logistics
- Port coordination and staged equipment delivery
- Crane placement and controlled setting of equipment
- Oversight of mechanical and electrical integration
- Commissioning coordination and operational transition
Project Environment
Severe weather events extended the project timeline and required adaptive scheduling, contingency planning, and consistent on-site leadership.
Infrastructure Impact
The completed upgrade increased emergency capacity from 3 MW to 4 MW, strengthening the resort’s resilience during hurricane season and enhancing long-term operational continuity.