Hyatt Regency Grand Reserve Rio Grande Puerto Rico info@pixelsanddots.com April 10, 2026

Hyatt Regency Grand Reserve

Rio Grande, Puerto Rico

The projects below represent generator infrastructure upgrades, system modernizations, and turnkey installations executed with disciplined planning and structured oversight. From broadcast facilities to mission-critical environments, each engagement reflects accountability, technical alignment, and execution when it matters most.

Project Overview

Led project management for the full decommissioning and replacement of 3 MW of emergency backup generation capacity at the Hyatt Regency Grand Reserve in Rio Grande, Puerto Rico.

The Challenge

The original three-week schedule was extended to nearly two months due to hurricane activity and severe storms.

The Approach

Continuous on-site leadership was required to maintain safety, sequencing, and execution integrity amid repeated weather disruptions.

Scope of Work

  • Decommissioning of two 1.5 MW generators
  • Installation of two 2 MW Caterpillar diesel generators
  • Coordination of international freight shipping and island logistics
  • Port coordination and staged equipment delivery
  • Crane placement and controlled setting of equipment
  • Oversight of mechanical and electrical integration
  • Commissioning coordination and operational transition
IMG_3531-puerto-rico-758x1000
7E509685-5CE6-4A16-8CAE-63C28E08A7AF-puerto-rico-600x797

Project Environment

This project required structured management within an active resort property during hurricane season.

Severe weather events extended the project timeline and required adaptive scheduling, contingency planning, and consistent on-site leadership.

Infrastructure Impact

The completed upgrade increased emergency capacity from 3 MW to 4 MW, strengthening the resort’s resilience during hurricane season and enhancing long-term operational continuity.